Oracle Pleasanton
Pleasanton, California
Oracle Pleasanton's office building is a 180,000 sqft space that houses a data center, computer lab, fitness center, and cafeteria. After working with Taylor Engineers this building received a Silver LEED Rating.
HVAC design for this project includes built up VAV chilled water air handlers serving VAV reheat boxes. To meet specific performance specifications computer labs are served by CHW fan coils and VAV boxes built for redundancy and economizer free cooling. Additionally, the chiller plant installed by Taylor Engineers provides high efficiency, water-cooled, variable speed screw chillers, selected in a pre-bid lifecycle cost analysis. The chiller plant also includes an integrated waterside economizer to serve the data center and computer labs giving them the power to run consistently at maximum efficiency.
Size (ft²)
180,000
Stories
N/A
Project Type
Office - Datacenter
Scope of Work
Full design and commissioning for HVAC, controls, plumbing, and fire protection.
Completed
2009
Owner
Oracle Corp.
Architect
Gensler
Contractors
Webcor Builders (GC)
ACCO (HVAC)
Photographer
References
Cliff Berry, Oracle
Ankit Somani, Oracle
Ken Morrison, Rockridge Group
Phil Williams, Webcor Builders